Following up on the progress of the sewage network extension project in Al-Musabbeh area in Rafah, funded by the Turkish Red Crescent Society, to serve about 1,000 people.
The Progress of Work on the Sewage Line Extension Project in Al-Musabbeh Area in Rafah City
Gaza / CMWU
As part of CMWU's approach of following up on and evaluating the various stages of project implementation, and verifying the integrity of the procedures followed during project implementation and their compliance with the plan prepared for the project, a joint committee from the Oversight and Audit Department and the Projects Supervision Department conducted a field visit to the project site, in order to learn about the progress of the project's implementation and its various elements in "Al-Musabbeh" area in Rafah city, south of the Gaza Strip.
It is worth noting that CMWU began, at the start of last week and funded by the "Turkish Red Crescent Society", implementing the project to extend sewage networks and household connections in Al-Musabbeh area, which serves about 1,000 people.
The project also targets filling in and eliminating cesspits in the targeted area, which cause numerous environmental problems for the area and its residents.