CMWU, funded by the Kuwait Fund, continues constructing the solar power plant (3.7 MW) at the Central Treatment Plant east of Khan Younis.
CMWU Continues Implementing the Solar Power Plant Construction Project at the Central Sewage Treatment Plant East of Khan Younis
Gaza – CMWU
CMWU continues implementing the project to construct the solar power plant "Phase Two" at the Central Sewage Treatment Plant east of Khan Younis governorate, funded by the Kuwait Fund for Arab Economic Development, managed by the Islamic Development Bank.
The project includes constructing a solar power plant at the Central Treatment Plant east of Khan Younis governorate with a capacity of 3.7 MWp, in order to operate the treatment plant for the greatest possible number of hours, particularly amid the continuing electricity outage crisis in the Gaza Strip.
The sewage treatment plant in Khan Younis governorate and its associated filtration basins, located east of the governorate, are considered among the strategic projects that have effectively contributed to upgrading the sewage collection and treatment system, and improving the health and environmental situation in Khan Younis governorate, by ending the suffering of a large proportion of the governorate's residents from the cesspit problem, and also ending the pollution of the seashore and benefiting from the treated water by injecting it into the groundwater aquifer.
The quantities of sewage arriving at the plant are also treated with high efficiency, with a removal rate of about 99%, and then filtered to the groundwater aquifer through the filtration basins established in Al-Fukhari town.